Pocatello reopens the West Benton Street bridge after a seven-month project

The Good Day Pocatello teamFrom the Nov. 17 edition · 1 min read · 2 sources

ShareEmailFacebookX

If you cross the Portneuf River downtown, the new West Benton Street bridge is open to traffic, the city announced Monday. Crews may still be in the area for the next few weeks doing minor finishing work.

The Benton Street bridge took until mid-November to reopen

  1. AprilConstruction began on the West Benton Street bridge.
  2. AprilThe city estimated the bridge would be finished by the end of September.
  3. JuneA city update put completion "this fall."
  4. Nov. 16The city announced the bridge is open to traffic.

Public Works Director Tom Kirkman said in June the old bridge was in "really, really bad shape" and the city was putting load restrictions on it. This was the last Portneuf crossing through the Army Corps of Engineers concrete channel that needed replacing. Much of the new structure was built off-site and craned into place.

  • Where: between South Hayes and South Grant avenues
  • Design: single-span concrete girder bridge on driven piles
  • Funding: , no local match
  • More projects: pocatello.gov/1002/Projects

The Benton Street bridge by the numbers

$2,268,437
in state grant money paid for the project
7 months
of construction, starting in April
5
other Portneuf crossings replaced earlier

Sources: Idaho State Journal, Local News 8

Read it in the full edition

All getting around news
  1. Idaho State Journal11 hours ago

    Christmas Night Lights Parade: Road closure and parking information, on Idaho State Journal

    POCATELLO — The city of Pocatello is assisting Historic Downtown Pocatello with road closures, parking restrictions, and traffic control for this year’s Christmas Night Lights Parade on Friday at 6:30